Raised road bridge connecting Thessaloniki port 6th quay already constructed bridge with Kalohoriou st

JV ELLINIKI TECHNODOMIKI S.A. - POLYTECHNIKI S.A., Final design, 2001, 2.435.000 €
Road bridge consisting of two separate branches, with a total length of 139,6m (15m + 5x20,8m + 20,6m = 139,6m) for the left branch, 67,4m (4x16,85m = 67,4m) for the right branch, and a maximum pier height of 7,5m. Continuous superstructure of solid slab, with slopping sides, rigidly connected to the piers. Pile foundations.
The final design was carried out in 2001, with a design budget of 2.435.000€, project owner EGNATIA ODOS S.A., construction by JV ELLINIKI TECHNODOMIKI S.A. - POLYTECHNIKI S.A., completed in 2002.